Case Study
From a full day on site followed by two more hours at the laptop, to a report waiting for him every night and his evenings back
Company
R&A Marine Services
Industry
Energy projects, Papua New Guinea and Australia
Problem
The daily site report took up to two hours of copying and retyping WhatsApp updates every evening, so it got pushed to early mornings or skipped.
What we built
- • A daily site report assistant that reads the day's updates from the site WhatsApp groups
- • Each report built in Martin's template, showing who reported every figure
- • Gaps and figures that don't match, flagged rather than guessed
- • A draft ready every evening for Martin to check and approve
Outcome
- ✔ From 2 hours a night to 15 minutes
- ✔ Up to 10 hours back every week
- ✔ A report every night, with no more skipped days
The Situation
Where things stood
R&A Marine Services is a family-led business working across Papua New Guinea and Australia, employing about 300 staff across shipping, telecommunications and energy projects.
Martin is the construction manager on a solar mini grid project in Kimbe. His site teams don't have email, so all day they post their progress into WhatsApp: loads delivered, measurements, earthworks and photos. Every evening Martin turns that into a daily site report for management, and the daily reports feed the monthly report to the client.
"We use so much WhatsApp, and you'd have to manually download. If we could link WhatsApp, we'd be laughing."
The Bottleneck
What was actually in the way
- Martin had to wait until his teams had posted everything, then start
- Every message and photo was copied across by hand, and the notes retyped
- His report template had to be pasted in every time, or the layout changed
- It took one and a half to two hours a night
- So it slid to early mornings, and some days it didn't happen at all
"Sometimes I'm skipping a day or two with my update, which I'm wanting to prevent. Sometimes I do it in the early hours of the morning."
The Fix
What we built
1. Mapping the report. Nina sat down with Martin, the project manager and the project's junior PM to map what the daily report needs to show, where every number comes from, and how it feeds the monthly report.
2. Building the assistant. Every evening at 7:30, the assistant reads that day's messages in the two site WhatsApp groups. It only reads: it never posts, reacts or deletes. It pulls the figures and photos into Martin's daily report template and notes who reported each figure. Anything that doesn't match gets flagged, and anything missing is marked "not reported", never guessed. When the draft is ready, a notification goes to Martin's phone.
3. Keeping Martin in charge. Martin reads the draft, changes what needs changing and types "approved". Only then is it saved and shared with the project team.
"Now it is giving me what I want. This is the format that I was wanting Claude to continue using."
He then used the same approach to build himself a morning task plan that's ready at 5am.
Tool layer
- Claude: the daily site report assistant, running on a nightly schedule
- WhatsApp Web: the two site groups, read-only
- Dropbox: where the reports are saved for the monthly report
The Outcome
What changed
- ✔The daily site report went from up to 2 hours a night to about 15 minutes
- ✔That's up to 10 hours back every week, and up to 500 hours a year
- ✔A report goes out every night, with no more skipped days
- ✔Every figure shows who reported it, and gaps are flagged
- ✔Site updates are no longer stuck in WhatsApp, so they can feed the monthly report
- ✔Martin built his own morning task plan using the same approach
The Human Payoff
What it actually meant
Martin used to finish a long site day with two more hours of copying and retyping, or leave it until dawn. Now the report is waiting for him. He checks it, approves it, and his evening is his own.
"The reporting that was done previously, it's so long and it takes ages. But now, as you set it up, it is much more faster for me."
Client Feedback
"Martin's daily reports are very useful, both for us internally."
Matt, Project Manager, R&A Marine Services, Papua New Guinea